Knocked a few more things off the list in the past few days....most notably the underfloor heat is installed and wired and actually working:)  It's going to take a few hours to prime the slab but once that's up to temp it should be pretty easy to keep those floors at a nice even temp that will keep our toes toasty.  I just wish we could have done this throughout the downstairs without costing an arm and a leg.  Oh well, at least we are heating the coldest surface in the house:)

I've added a few things to the list too...most of it's finish stuff now (nitty gritty little things) but for the most part, a bulk of the kitchen is DONE! wahooooo....It's such a pleasure to cook in there now!

The list:
- install plinth and filler wood
- buy the remaining handles and install them (all the uppers are handle-less right now)
- install outlets for microwave
- install microwave
- sand and prime the new wall board where the pantry came out
- install new light switch for under cabinet lighting - run the line too
- install under cabinet lighting
- new backsplash needs installed
- whole kitchen needs painted
- purchase and hang new curtains (color dependent on the walls)
- clean up the mess!
- new cabinets need installed (70%)
- install temp sink and plumbing
- install door fronts, hardware, drawers (50%)
- remove and purchase new dishwasher
- new countertop needs ordered (and then installed)
- permanent plumbing needs installed
- finish the electrical for the heated floors
- scrub every surface in the rest of the house and clear it of dust